MEP is an acronym used for Mechanical,
Electrical and Plumbing systems for building projects. With the increasing complexity and
functionality of each system, MEP activities are not confined to the
traditional mechanical, electrical and plumbing system but also include fire
protection, gas piping, process piping, pneumatic tubing, data systems
etc. This article assumes that the
design has been completed by ‘Design Consultants’ to a certain stage and then
handed to ‘Installation Sub-Contractors’ who will validate the design and value
engineer the design through the process of spatial coordination and procurement
of components to meet the requirements of the design. The coordination of Mechanical, Electrical
and Plumbing (MEP) systems amongst themselves and with other building systems
including architectural and structural disciplines is a critical, challenging
and time consuming task, especially in complex building projects with intense
MEP requirements. The coordination
process of Mechanical, Electrical and Plumbing (MEP) systems involves defining
the exact location of each building system component throughout the building
within the constraints of the envelope defined by the architectural and
structural systems to comply with diverse design and operations criteria
avoiding any interferences/clashes amongst building systems. Assuming that most
companies undertake the task of MEP Coordination, without which the site
installation from a ‘design only’ set of drawings would be too much of a risk,
there are two ways by which the following process takes place:
2D
MEP Coordination: The process starts with the
design from the Design Consultant. The
Sub-Contractor team will manually update the 2D CAD drawings or create their
own set from the start. In creating
these drawings a number of sections will be drawn and frequent attention given
to ceiling void spaces in which the systems and services are being laid
out. In an ideal world 2D MEP
Coordination can work as long as all services and systems are assessed
adequately and then drawn into a 2D drawing.
The sizes of the systems would need to be manually added as would the
heights and distances from gridlines or walls.
The contractor will have teams of people for each system (HVAC,
plumbing, electrical etc) creating their drawings based on the architectural
ceiling void. In this method, there is
no automated system to identify the conflicts in the MEP system and therefore
there is a high degree of reliance on the intuition, imagination, technical
knowledge and experience of the team members to lay out the services without
site teams experiencing clashes.
Visualizing the potential clashes is made more difficult due to changes
in ceiling profiles, not to mention the challenge of having to understand the
impact of all systems as well as structural and architectural elements that may
impede or impact a system or service route.
What makes things worse is that a third party cannot easily review the
drawings for any errors, nor can the design be easily reviewed or communicated
with a project team. Additionally, if
there are changes to the design or procurement-led changes then the process of
undoing and re-doing 2D MEP Coordination projects becomes very cumbersome. The inherent weaknesses of 2D CAD software
also come into play; one can draw something of one size and label it as
something completely different. As the
systems and services drawings are not checked in some form of automated method
there is no guarantee that the 2D MEP coordination process will generate a
clash free drawing. During the time of complex projects, it requires multiple
section viewings which consume a lot of time.
These time commitments come with additional costs to each contractor.
3D MEP Coordination : This process is more
collaborative and allows the ability to communicate the progress of the project
quickly and easily, providing 3D visuals that resemble the final system and
service installation. It starts with a
clear direction in terms of spatial zoning which is then used as the basis to
start modeling the HVAC, piping, plumbing and electrical services. As the architectural and structural models
form part of the model, it is easier to insert services and systems without
creating clashes. Once the model is
complete and all systems and services have been added, the ability to identify
problems becomes much easier compared to the 2D Coordination method. Firstly,
one is able to walk through the model using roaming software to review the
model and, secondly the use of clash detection software, such as Navisworks,
highlights all clashes whether these are systems against other systems or
systems against structure or architecture.
Once highlighted, all clashes can then be corrected during the coordination
stage of the project. Only once the
model is interference free are drawings created. This leads to another set of benefits, unlike
2D coordination where each section must be drawn, the 3D software allows
creation of sections that are directly taken from the model. Additionally, as the 3D software is so
intelligent, the sizes of systems are directly taken from the 3D model and
therefore there is no chance of services or systems being modelled as one size
and then labelled as another. Beyond the
coordination stage, there are several other benefits from the 3D model,
including use during facilities management, energy analysis and so on.
Irrespective of the MEP Coordination
method used, the need for MEP Coordination arises due to the lack of detailed coordination during the
design stage. Additionally the need for
fabrication and installation of building systems in accordance with industry
and Sub-Contractor best practice requires MEP Coordination to be carried out by
them.
The 2D MEP Coordination process provides a limited interference-checking
capability and therefore can and will result in more problems on site including
additional re-work, change orders and inflating budgets. All of this makes 3D MEP Coordination a more
efficient and the increasingly preferred method for the long term.
No comments:
Post a Comment