Monday, 13 January 2014

Typical Stages Involved in MEP Coordination

One of the most integral practices undertaken in the pre-construction phase, MEP coordination demands special attention from all the AEC professionals involved in a project. This process ensures that the building’s architectural design and its structural framework don’t interfere or clash with its Mechanical, Electrical, Plumbing or Fire Protection systems. While the MEP coordination process may vary from firm to firm depending on the client’s requirements and the level of details (LOD) sought, following are the typical stages involved in the same:-

1. Review of Consultant Design Drawings and Architectural/Structural Plans

In this preliminary stage, the firm responsible for MEP coordination normally receives single-line drawings from MEP consultants or contractors. Additionally, the architectural and structural plans are analysed in detail. Apart from evaluating these drawings and layouts for consistency with schematics, their MEP specifications are studied. Based on this analysis, the MEP coordination services provider lays out a coordination roadmap.

2. 3D Model Creation

Using the consultant design drawings received in the initial stage, the MEP coordination services provider creates an accurate 3D model, by either using Revit or AutoCAD. This model shows all the MEP services within the architectural and structural limitations of the building. The 3D model completed here lays the groundwork for several other important construction-related drawing sets -- plans, sections or elevations. Furthermore, this 3D model will be used for client inputs and for creating detailed walkthroughs.

3. Clash Detection and Resolution

In this stage, the MEP coordinating services provider evaluates the 3D model, created in the previous stage, for conflicts and clashes between the architectural elements and the MEP systems. This is done using Navisworks, a specialist interference-checking software application. Any inconsistencies, including the geometry-related hard clashes, the clearance clashes, and workflow clashes, if any, are detected here and feasible alternatives for the same are provided to the client.

4. Creation of Coordinated Drawings and Sections

Once the 3D model is tested for horizontal and vertical coordination and clearance, coordinated drawing sets are prepared to show how mechanical, electrical, plumbing, and fire-protection systems work together in the same space. Besides, to make sizes clear for each discipline, additional notes may be added. The coordinated drawings form a ready reference for individual service-by-service drawings. In addition to this, firms responsible for handling MEP coordination may take section, elevation and isometric views from the same 3D model and use them to explain to the clients and detail the layouts.

5. Creation of Detailed Service Drawings

At this stage, each of the single service-by-service drawings are created and details related to their sizes, heights, and distances from gridlines, are added for further clarity. While these drawings are used by site installation teams, they also form the basis for fabrication drawings.

6. Creation of Fabrication Drawings, Spool and Hangar Drawings

In case the scope of work requires, then the individual services drawings are used to create fabrication drawings by either using traditional detailing or using FAB-MEP software. These drawings display fabrication details for ductwork and can be directly recognised by the CNC machines for production purposes.

If needed, the MEP coordination team also details elements of the model to create spooling data for production teams. Apart from this, the firm may also map out and then detail the hangers for each drawing. Once mapped out, the hangar details are shown on a schedule for the production teams.
Depending on the scope of the project, some of the above stages may be excluded by the MEP coordination services providers. However, each phase is crucial for a smooth completion of the project without any delays, cost overruns, and abrupt design changes.

7. As-Fitted Changes

This final stage involves making changes to the model and the drawings due to any site based changes or deviations from the construction drawings.  In cases where the coordination exercise has been well executed and the installation has followed the construction drawing instructions and layouts, the changes to the as-fitted (also known as as-built and as-installed) drawings are minimal.

Wednesday, 16 October 2013

Benefits of BIM Services for Pre-Construction Planning are Multifaceted and Long-Term

In the AEC industry, the advent of building information modeling (BIM) concept was viewed by many as an evolution to better 2D and 3D computer-aided design (CAD) techniques. Very few saw it as an interdisciplinary, collaborative tool that would drastically change the design-build project workflow, the management structure of AEC firms, the teaming models, the delivery standards, and the role of key disciplines involved.

As opposed to the vertical communication channels and delivery methods required by the traditional design-build approaches which mainly employ CAD, BIM necessitates an open and integrated horizontal collaboration channel between all the key stakeholders of the project: facility owners, designers/architects, MEP (M&E) engineers, consultants and contractors. To realise the benefits of employing BIM services as compared to 3D CAD modelling tools, firms need to significantly invest in knowledge/skills development, personnel training, management restructuring, and software tools. However, more than these tangible investments, AEC companies need a complete change in mindset in case they want to adopt BIM for their projects.

Whilst many professionals, especially those from small and medium-sized firms, see it as an extension of 3D CAD, BIM is anything but 3D CAD. BIM services involve extensive pre-construction planning and multidisciplinary coordination to virtually model building facilities using smart parametric objects embedded with rich accurate information. This intelligent model then can be used by all stakeholders to extract respective views and relevant information thereby resulting in timely decision-making and project delivery.

Though BIM and 3D CAD are not mutually exclusive to each other, they have major differences as far as the approach and the output is concerned. In traditional 3D CAD, depending on the scope of project, architects prepare a set of construction drawings, including the plans, sections, and elevations. Since all these views are independent entities, any change in one view has to be manually updated in others. As a result, the process is not only time-consuming but also increases the scope for errors.

On the contrary, a building information model contains the architectural, structural and MEP system models of the proposed facility. It is prepared during the design and planning stage using details from all the key stakeholders including designers, engineers, MEP contractors, and subcontractors. Since a single database-driven model represents details required by all disciplines, any changes made by any of the team members are automatically updated across the model to plans, sections and elevations. Hence, all the project team members are updated on all the changes made by others thereby saving time, reducing cost resulting from duplication of efforts, and increasing the overall quality of construction drawing sets. As a result, making small changes to the architectural plan would result in those changes appearing simultaneously in the section, elevation or schedule for the same change to the plan.

Furthermore, the building blocks of 3D CAD models are lines, circles, arcs, and other graphical entities, which lack the flexibility of data analysis. These models only serve as geometric objects devoid of detailed parameters which are required by the entire AEC supply chain. In contrast, BIM models comprise building elements and intelligent systems, including columns, beams, and walls, which contain rich data related to parameters. If needed, additional parameters can be added to the pre-existing ones for more detail. And, this rich data can be effectively shared across disciplines for rich collaboration and on-time delivery.

Nevertheless, the success of any project which employs BIM depends mainly on factors which include the richness of information embedded in the 3D models, the degree of openness in the interdisciplinary data-sharing and collaboration standards, and the level of mutual trust among all the professionals involved. If prudently planned and implemented, a BIM model not only represents the essential building elements in detail; valuable information concerning spatial coordination, geographic location, quantity take-offs, material requirements, time schedule, and project cost can be extracted when needed.

In essence, well-planned BIM services help accurately represent the entire project design lifecycle. Though preparing for and implementing BIM strategies requires considerable investment of time, money, and effort, its benefits are multi-faceted and long-term. Employing BIM modelling can not only help in more effective design and construction but also offers pre-fabrication and facilities management advantages.